{"id":869,"date":"2022-12-12T10:04:49","date_gmt":"2022-12-12T15:04:49","guid":{"rendered":"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=869"},"modified":"2025-11-14T09:53:07","modified_gmt":"2025-11-14T14:53:07","slug":"eversource-transmission-line-project-information","status":"public-archive","type":"post","link":"https:\/\/sudbury.ma.us\/selectboardsoffice\/2022\/12\/12\/eversource-transmission-line-project-information\/","title":{"rendered":"EVERSOURCE Sudbury to Hudson Transmission Line Project"},"content":{"rendered":"<p>On February 2, 2016 Eversource Energy made a presentation before the Sudbury Select Board to introduce the Sudbury to Hudson Transmission Reliability Project. The project proposes to install a 115-kV transmission line through areas of Hudson and Sudbury and smaller sections of Marlborough and Stow.<\/p>\n<p>Having obtained the required approvals, Eversource began construction on their Sudbury-Hudson Transmission Line Project in the fall of 2022: <a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/10\/S-H-Start-of-Construction-Letter-10.07.22.pdf?version=c613e0de9209dac4fef2ad7a4835720d\"><strong>Please see <span style=\"text-decoration: underline\">Start of Construction Notice<\/span> <em>10\/11\/22<\/em><\/strong><\/a>. The Town worked closely with resident groups, staff, committees and special counsel to raise concerns about the project, which will disturb land along the MBTA-owned Right of Way (approximate project route shown in purple below). The installation of underground power lines along the route will be followed by construction of Sudbury\u2019s portion of the <strong>Mass Central Rail Trail (MCRT)<\/strong>.<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/09\/Eversource-Underground-Transmission-Line-Project-Location-Map.pdf?version=9ecb770ec251a8ac68c89feb11bc9354\"><img decoding=\"async\" loading=\"lazy\" class=\"aligncenter wp-image-3011 size-large\" src=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2016\/03\/Eversource-Underground-Transmission-Line-Porject-Location-Map-1024x763.jpg\" alt=\"Map of the Eversource Transmission Line Project, the Sudbury route\" width=\"584\" height=\"435\" srcset=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2016\/03\/Eversource-Underground-Transmission-Line-Porject-Location-Map-1024x763.jpg 1024w, https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2016\/03\/Eversource-Underground-Transmission-Line-Porject-Location-Map-300x223.jpg 300w, https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2016\/03\/Eversource-Underground-Transmission-Line-Porject-Location-Map-768x572.jpg 768w, https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2016\/03\/Eversource-Underground-Transmission-Line-Porject-Location-Map-1536x1144.jpg 1536w, https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2016\/03\/Eversource-Underground-Transmission-Line-Porject-Location-Map-2048x1525.jpg 2048w, https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2016\/03\/Eversource-Underground-Transmission-Line-Porject-Location-Map-403x300.jpg 403w\" sizes=\"(max-width: 584px) 100vw, 584px\" \/><\/a><\/p>\n<p>As Eversource moves forward with the project, Town staff and consultants will work with Eversource and their construction contractor Bond to ensure the work complies with established conditions. Eversource will provide updates as the project progresses.<\/p>\n<p>&nbsp;<\/p>\n<h2>Construction Updates<\/h2>\n<p>Click hyperlinks below for emails and notifications sent to residents from Eversource.<\/p>\n<p><strong>2025<\/strong><\/p>\n<ul>\n<li><a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2025\/11\/Sudbury-Hudson-Post-Construction-2025-09-25-Final.pdf?version=bd1d5dc27fe7d815046d39250adf5fad\">Post-Construction EMF Measurements: Road Crossings of the Sudbury to Hudson Transmission Line in Sudbury<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2025\/05\/EV-Update-05.23.25.pdf?version=897bdf7161172fe334c26576e1c027a7\">May 23, 2025 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2025\/05\/EV-Update-05.06.25.pdf?version=93d9d3e6c6724a39f59151f2d49a8abe\">May 6, 2025 Project Update<\/a><\/li>\n<\/ul>\n<p><strong>2024<\/strong><\/p>\n<ul>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/12\/EV-Update-12.27.24.pdf?version=5ce4971361c725785d1905cad922d9af\">December 27, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/12\/EV-Update-11.22.24.pdf?version=50f2b50d5479fceee0cfe83002627af9\">November 22, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/11\/EV-Update-11.15.24.pdf?version=d8349fd51f19a15ed280645d92ec3969\">November 15, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/11\/EV-Update-11.08.24.pdf?version=48d3c91917732c334c8957655842a69a\">November 8, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/10\/EV-Update-10.31.24.pdf?version=41228c0ca5e7b59fe68ddb6e056dbb88\">October 31, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/10\/EV-Update-10.25.24.pdf?version=432f71949d902992ef60dc81f1351e02\">October 25, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/10\/EV-Update-10.18.24.pdf?version=963d09432001bef904dc18052cebc114\">October 18, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/10\/EV-Update-10.11.24.pdf?version=5330a56ed082bc149ad2b06dcc72a71b\">October 11, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/10\/EV-Update-10.04.24.pdf?version=d6a3660e6174bb828565378ef55bae26\">October 4, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/09\/EV-Update-09.25.24.pdf?version=0c8227b90e015c8f656003fd8e0c90a3\">September 25, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/09\/EV-Update-09.20.24.pdf?version=cd55d62cc91fa3d769af8f6a181b3d36\">September 20, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/09\/EV-Update-09.13.24.pdf?version=367e82a4290b78fc896ada7581186333\">September 13, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/09\/EV-Update-09.06.24.pdf?version=a3f616ad5fd4ed8bd1c8a631a42c903c\">September 6, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/08\/EV-Update-08.30.24.pdf?version=217f7d6b7ae12e7d0aff5457b675c3f1\">August 30, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/08\/EV-Update-08.23.24.pdf?version=9e67478b9decd6dee70e02a8d162e5d1\">August 23, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/08\/EV-Update-08.16.24.pdf?version=0088ea3e0f97d4917382abf1ed0b702f\">August 16, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/08\/EV-Update-08.09.24.pdf?version=5474e3efc3d9150d7ea5cbb637aa3d8b\">August 9, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/08\/EV-Update-08.02.24.pdf?version=3807fd2ecde90f21b7380f92c00e3a62\">August 2, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/07\/EV-Update-07.19.24.pdf?version=5846aa8ed951e228275ec26faaeac95d\">July 19, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/07\/EV-Update-07.12.24.pdf?version=303a3c993eeb8790de5d54bfc34846f9\">July 12, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/07\/EV-Update-07.03.24.pdf?version=d68071139d43f4a545bb862c1e50cd15\">July 3, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/07\/EV-Update-06.26.24.pdf?version=81218f937debf3e6a416070fa7927c5e\">June 26, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/07\/EV-Update-06.21.24.pdf?version=b13e8eb86ac7e315f532db42e337c3d5\">June 21, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/07\/EV-Update-06.14.24.pdf?version=3131ccdbe63f328ab1555e75252d49b8\">June 14, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/06\/EV-Update-06.07.24.pdf?version=ffbaea8618279f67ed627b1459bb2245\">June 7, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/05\/EV-Update-05.31.24.pdf?version=aa35129657a4b7162fe6b753cf07d2b6\">May 31, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/05\/EV-Update-05.24.24.pdf?version=01f1b75117d42a79f3b39a33c223d008\">May 24, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/05\/EV-Update-05.17.24.pdf?version=87b8a3f52dc0e1dd209086d415263a8d\">May 17, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/05\/EV-Update-05.10.24.pdf?version=adc913ec552e0cf383153761ccb1b4ff\">May 10, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/04\/EV-Update-04.26.24.pdf?version=ac6ef29daf839fcde09f5d05bfef80b8\">April 26, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/04\/EV-Update-04.19.24.pdf?version=e3d5489cb04a36f68855e6963fd90c6c\">April 19, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/04\/EV-Update-04.12.24.pdf?version=6b6a2b48861144e7426f539cea10b55b\">April 12, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/04\/EV-Update-04.05.24.pdf?version=5516f41e0379207f2c5ab4f5c1a26bcf\">April 5, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/03\/EV-Update-03.29.24.pdf?version=f998a8bde8bff7f4cec45467f44c16fc\">March 29, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/03\/EV-Update-03.21.24.pdf?version=9d2557f6e49ab529bd0573f4540ba803\">March 21, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/03\/EV-Update-03.14.24.pdf?version=1e0e12de14e1b32808632a8be79e8b3a\">March 14, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/03\/EV-Update-03.07.24.pdf?version=10c52ca4fdabed2b56405febc0f53672\">March 7, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/02\/EV-Update-02.28.24.pdf?version=ede360762e579c051c6800f80631b8c3\">February 28, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/02\/EV-Update-02.22.24.pdf?version=ede360762e579c051c6800f80631b8c3\">February 22, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/02\/EV-Update-02.08.24.pdf?version=a0e6cad33d7319c7f7dcd0ef453a084c\">February 8, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/02\/EV-Update-02.01.24.pdf?version=197ee0078c25607fb72014c5ac94e1a7\">February 1, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/01\/EV-Update-01.25.24.pdf?version=72e80a5c89b106a0d69d62b46783e315\">January 25, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/01\/EV-Update-01.18.24.pdf?version=1be2b3b62ba0c6d077654c38950dd186\">January 18, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/01\/EV-Update-01.11.24.pdf?version=d4a4bd3e93dfe4298322b0a1c4142c63\">January 11, 2024 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2024\/01\/EV-Update-01.04.24.pdf?version=3f1ee46c65c1d71ef2ec9ead764f85b3\">January 4, 2024 Project Update<\/a><\/li>\n<\/ul>\n<p><strong>2023<\/strong><\/p>\n<ul>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/12\/EV-Update-12.28.23.pdf?version=9a60b2a0c85289711e6a3446b8ed31cb\">December 28, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/12\/EV-Update-12.21.23.pdf?version=2847ab475c4e1e49153c7104b850ff30\">December 21, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/12\/EV-Update-12.14.23.pdf?version=e9a9ca585301de2c1cb597d8a11694c7\">December 14, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/12\/EV-Update-12.08.23.pdf?version=19c1ea5be9cf6d40b4a0810176482a2b\">December 7, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/11\/EV-Update-11.30.23.pdf?version=cb47aa7dbf1a1cc9f686d25e5da05900\">November 30, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/11\/EV-Update-11.22.23.pdf?version=f31d6c65ebbf1856cb4c2458ffc1eaae\">November 22, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/11\/EV-Update-11.16.23.pdf?version=3db7db8e9857cd2d47d37701635a8b5c\">November 16, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/11\/EV-Update-11.09.23.pdf?version=ad6e065da9adabd59abd03e8c16c74da\">November 9, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/11\/EV-Update-11.02.23.pdf?version=a19a6a81a306c622db46b77f0378f9d1\">November 2, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/10\/EV-Update-10.25.23.pdf?version=603d2cb358e0018b694cfeb62d60c7fd\">October 25, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/10\/EV-Update-10.18.23.pdf?version=fbc4800d3c67a1f582edbd9f70ed3ddd\">October 18, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/10\/EV-Update-10.11.23.pdf?version=dedb4c0be63e320463901b90f577ecc9\">October 11, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/10\/EV-Update-10.05.23.pdf?version=dac6068c73aa4bf75557bddf1c415427\">October 5, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/09\/EV-Update-09.27.23.pdf?version=c6de441b3ca85cf11e09314fad07f2da\">September 27, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/09\/SH_Sudbury_Rd-cross-DH_Fall23.pdf?version=f3d511a10bfde32e67a097ab69eca8cd\">Construction at Road Crossings<\/a> &#8211; September 27, 2023<\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/09\/EV-Update-09.20.23.pdf?version=e1d6f897183ec4866a8e82874c2a6fb6\">September 20, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/09\/EV-Update-09.13.23.pdf?version=ac85b89dc7b5cdc7001461629f9ae7fc\">September 13, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/09\/EV-Update-09.06.23.pdf?version=2cad18d2f6ffb73012131ea9cc5c3ba6\">September 6, 2023 Project Update<\/a><\/li>\n<li>Eversource will conduct extended work hours (7 a.m. to 8 p.m.) on Dutton Road in Sudbury on Tuesday, 9\/5\/23 during the rescheduled water line work related to the 115-kV Sudbury-Hudson Project.<\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/08\/EV-Update-08.30.23.pdf?version=9a15dded002344d4e6b798bf0ec252ef\">August 30, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/08\/EV-Update-08.23.23.pdf?version=716fc8be46020bb48b90916ab32fe7cd\">August 23, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/08\/EV-Update-08.17.23.pdf?version=b24ff907f0a548578848f959a99aa931\">August 16, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/08\/EV-Update-08.09.23.pdf?version=4b40e0e9b742b48ae124f4ab7e7df886\">August 9, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/08\/EV-Update-08.04.23.pdf?version=8ec7d4d9bffa6bb4f8786cd67adc0a0d\">August 4, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/07\/EV-Update-07.28.23.pdf?version=5c7c829fac86206aa948a464cfab6c83\">July 28, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/07\/EV-Update-07.21.23.pdf?version=26f4d0256ad5b31f63ce24595f8070af\">July 21, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/07\/EV-Update-07.14.23.pdf?version=15c3b17bb605f33d7b029b8c7dd9195f\">July 14, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/07\/EV-Update-07.07.23.pdf?version=f2f9a7ed64a6b6ddad982ee6cf9ef186\">July 7, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/07\/EV-Update-06.30.23.pdf?version=754cf3d7ddd394291a71d17484a03081\">June 30, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/06\/EV-Update-06.23.23.pdf?version=de59994e46ad41b0a23dfc5770173a3d\">June 23, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/06\/EV-Update-06.16.23.pdf?version=aed893e18b38e6b4f2c22e41b38f2b99\">June 16, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/06\/EV-Update-06.09.23.pdf?version=7d9d64e0e3c2746369b09ca3f9143c4c\">June 9, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/06\/EV-Update-06.02.23.pdf?version=bd2af3bb65717f134934e2289bcb9ca7\">June 2, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/05\/EV-Update-05.31.23.pdf?version=8213f2337b63eeea36645911d559630f\">May 31, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/05\/EV-Update-05.24.23.pdf?version=fac260c72786ce9befd1adbc3d022100\">May 24, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/05\/EV-Update-05.17.23.pdf?version=9ae7481638574c01e5e4a82e104a9a77\">May 17, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/05\/EV-Update-05.10.23.pdf?version=90591be8eb265077e431e6ae2f9c34ba\">May 10, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/05\/EV-Update-05.03.23.pdf?version=eb04373154dfa4fdaa94f1e519bc1cc7\">May 3, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/04\/EV-Update-04.26.23.pdf?version=26e53ea5b5b6f21b64b0c76ce0db75b9\">April 26, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/04\/EV-Update-04.19.23.pdf?version=7cb0f8f8ed05d7d8772df720ae16d0e2\">April 19, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/04\/EV-Update-04.12.23.pdf?version=980149e12ef5d811edb30e81840f2315\">April 12, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/04\/EV-Update-04.10.23.pdf?version=7c6724b443f638f4060476841ab4a580\">April 10, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/04\/EV-Update-04.05.23.pdf?version=c526bdbb67e27ce2480175fb02829ee6\">April 5, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/03\/EV-Update-03.29.23.pdf?version=a9f66674593f0851040625b720b26461\">March 29, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/03\/EV-Update-03.22.23.pdf?version=05055311600696230142be090671461f\">March 22, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/03\/EV-Update-03.15.23.pdf?version=c16c5b974e3e074a7e8247a84e30a9a4\">March 15, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/03\/EV-Update-03.08.23.pdf?version=74b441a9ceb2dc0b4de519eb171223da\">March 8, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/03\/EV-Update-03.01.23.pdf?version=b514f38a59471f180784f6049e900a5d\">March 1, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/02\/EV-Update-02.22.23.pdf?version=b24d64c4c1269d8b1f0b05cee1f22d4f\">February 22, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/02\/EV-Update-02.21.23.pdf?version=10ecc0785f325889f4e975dc43d16995\">February 21, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/02\/EV-Update-02.15.23.pdf?version=6b11ed79b5b142385b175c84f1175f00\">February 15, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/02\/EV-Update-02.01.23.pdf?version=13c22c94cce25a33616985abc400dc1a\">February 1, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/01\/EV-Update-01.25.23.pdf?version=40979f7bbde45f9717f7b75e52336847\">January 25, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/01\/EV-Update-1.18.23.pdf?version=cb7cb0c0c978bca6d6d7e7b488e1070e\">January 18, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/01\/EV-Update-01.11.23.pdf?version=e39c368f96341897b0d3cb4e23ea4b8b\">January 11, 2023 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/01\/EV-Update-1.4.23.pdf?version=722af033e08fddffed1d61829f008045\">January 4, 2023 Project Update<\/a><\/li>\n<\/ul>\n<p><strong>2022<\/strong><\/p>\n<ul>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/12\/EV-Update-12.28.22.pdf?version=f32ceba6ebce563ca00261fa96e9b7a6\">December 28, 2022 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/12\/EV-Update-12.21.22.pdf?version=44540139f7da94cbff9a70983568af8f\">December 21, 2022 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/12\/EV-Update-12.14.22.pdf?version=af0a85494cfd75700f603a8de709175f\">December 14, 2022 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/12\/SH_Sudbury-MBTA-Corridor-Vegetation-Clearing-December-2022.pdf?version=d21effff1f5e6453238a7d7378afdb66\"><span style=\"color: #0000ff\"><strong>Vegetation Clearing Notification<\/strong><\/span> 12.7.22<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/12\/EV-Update-12.07.22.pdf?version=3ee9b0db13f21700518da42f29957e53\">December 7, 2022 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/EV-Update-11.30.22.pdf?version=b30af7b7ea981b485349267a83c7c8e9\">November 30, 2022 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/EV-Update-11.23.22.pdf?version=eefbd2efe68f8777e20a690c884ee1d6\">November 23, 2022 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/EV-Update-11.16.22.pdf?version=2ac4737ce38de2b04d96b28cccad1c20\">November 16, 2022 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/EV-Update-11.11.22.pdf?version=f6eb45aea51bbe50ff397263dcbfb368\">November 11, 2022 Project Update<\/a><\/li>\n<li><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/EV-11.9.22-update.pdf?version=bed3f9bf794ed42b39d5075dd2a05ebc\">November 9, 2022 Project Update<\/a><\/li>\n<li><a class=\"\" title=\"\" href=\"https:\/\/conta.cc\/3DzoWXS\" target=\"\" rel=\"noopener\" data-di-id=\"di-id-7f13168a-1013520\">November 2, 2022 Project Update<\/a><\/li>\n<li><a class=\"\" title=\"\" href=\"https:\/\/conta.cc\/3gMNcyc\" target=\"\" rel=\"noopener\" data-di-id=\"di-id-7f13168a-bf882e57\">October 26, 2022 Project Update<\/a><\/li>\n<li><a class=\"\" title=\"\" href=\"https:\/\/conta.cc\/3CRGFJK\" target=\"\" rel=\"noopener\" data-di-id=\"di-id-7f13168a-a9cc1f77\">October 20, 2022 Project Update<\/a><\/li>\n<\/ul>\n<p>&nbsp;<\/p>\n<h3>Contact Information<\/h3>\n<p>Residents with questions, comments or concerns about the project are encouraged to contact Eversource via the following:<\/p>\n<p><strong>Email<\/strong> <span style=\"text-decoration: underline\"><a href=\"mailto:ProjectInfoMa@eversource.com\">ProjectInfoMa@eversource.com<\/a><\/span><\/p>\n<p><strong>Phone<\/strong> 1-833-836-0302<\/p>\n<p><strong>Resident Support Office Hours <\/strong>In November and December 2022, Eversource held open office hours in Sudbury and Hudson. Resident Support Office Hours offered an opportunity to learn more about the project and ask questions with Eversource Field Outreach Representative Brianna Germain. Future office hours dates and locations will be posted as they are scheduled.<\/p>\n<p>&nbsp;<\/p>\n<h3>Construction Information &amp; Project Updates<\/h3>\n<p><img decoding=\"async\" loading=\"lazy\" class=\"alignnone wp-image-3140\" src=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/Info-Icon-300x300.jpg\" alt=\"\" width=\"27\" height=\"27\" srcset=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/Info-Icon-300x300.jpg 300w, https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/Info-Icon-150x150.jpg 150w, https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/Info-Icon.jpg 547w\" sizes=\"(max-width: 27px) 100vw, 27px\" \/>&nbsp;<a href=\"https:\/\/www.eversource.com\/content\/ema-c\/residential\/about\/transmission-distribution\/projects\/massachusetts-projects\/sudbury-to-hudson-project\"><span style=\"color: #0000ff\"><strong><span style=\"text-decoration: underline\">EVERSOURCE TRANSMISSION LINE<\/span> <span style=\"text-decoration: underline\">PROJECT INFORMATION PAGE<\/span><\/strong><\/span><\/a><\/p>\n<p><em>The Sudbury to Hudson Transmission Reliability Project page of the Eversource website&nbsp;contains information about the project and will be updated as construction progresses.<\/em><\/p>\n<p style=\"text-align: left\"><span style=\"color: #0000ff\"><strong><img decoding=\"async\" loading=\"lazy\" class=\"alignnone wp-image-3108\" src=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/walker-icon.jpg?version=3e042c7fe800ca1a8c5c5fa42dc43043\" alt=\"\" width=\"27\" height=\"27\" srcset=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/walker-icon.jpg 300w, https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/walker-icon-150x150.jpg 150w\" sizes=\"(max-width: 27px) 100vw, 27px\" \/> <\/strong><a style=\"color: #0000ff\" href=\"https:\/\/sudbury.ma.us\/conservationcommission\/?p=4352\"><strong><span style=\"text-decoration: underline\">TRAIL CONNECTIONS<\/span>&nbsp;<\/strong><\/a><\/span><span style=\"color: #ff0000\"><em><br \/>\n<span style=\"color: #000000\">During Project Construction<\/span><\/em><\/span><\/p>\n<p style=\"text-align: left\"><strong><img decoding=\"async\" loading=\"lazy\" class=\"alignnone wp-image-3107\" src=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/calendar-icon.jpg?version=7100546647714cdffe911a529aacf10e\" alt=\"\" width=\"25\" height=\"25\" srcset=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/calendar-icon.jpg 300w, https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/calendar-icon-150x150.jpg 150w\" sizes=\"(max-width: 25px) 100vw, 25px\" \/> <a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/10\/Bond-EVS-Sudbury-to-Hudson-115kV-Schedule-Update-05-DD01Oct22.pdf?version=fe0a8276557a4fa63454e9b6088ae639\"><span style=\"text-decoration: underline\"><span style=\"color: #0000ff;text-decoration: underline\">PROJECT SCHEDULE<\/span><\/span><\/a> <\/strong><strong><br \/>\n<\/strong><span style=\"color: #ff0000\"><span style=\"color: #000000\"><em>DRAFT &#8211; SUBJECT TO CHANGE<\/em><\/span>&nbsp;<\/span><\/p>\n<p><span style=\"text-decoration: underline;color: #0000ff\"><a style=\"color: #0000ff\" href=\"https:\/\/lp.constantcontactpages.com\/su\/r9TWGE6\/SH\"><strong>SIGN-UP FOR UPDATES<\/strong><\/a><\/span> Sign up to receive project construction updates via email.<\/p>\n<p><span style=\"color: #0000ff\"><a style=\"color: #0000ff\" href=\"https:\/\/www.google.com\/maps\/d\/viewer?mid=1dxeo_lDV5_Yvm8_c0ZF-bmh3u0HEnXUr&amp;ll=42.37815342674655%2C-71.4767534&amp;z=13\"><span style=\"text-decoration: underline\"><strong>INTERACTIVE PROJECT MAP<\/strong><\/span><\/a><\/span> Track project progress.<\/p>\n<p>&nbsp;<\/p>\n<h3>Mass Central Rail Trail Update<\/h3>\n<p>MassDOT held <a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2023\/02\/PF-610660-VDPH-Hearing-Flyer.pdf?version=1cc2ec86e620dfe88d0c6c71769d2c82\"><strong><span style=\"text-decoration: underline\">Virtual Design Public Hearing: MCRT Sudbury\/Wayland Rail to Trail<\/span> <\/strong><\/a>on <strong>Thursday, March 2<\/strong> at <strong>6PM<\/strong>. This Design Public Hearing is for the portion of the MCRT project that will run from the Eversource substation near The Coolidge (address of approximately 163\/183 Boston Post Road) and head EASTWARD into Wayland to the Wayland Library on Route 27\/126.<\/p>\n<p>&nbsp;<\/p>\n<h3>Project History &amp; Information<\/h3>\n<p>Please see links and resources below to learn more about the Eversource Transmission Line project and Sudbury&#8217;s response.<\/p>\n<p>&nbsp;<\/p>\n<p><strong>Soil Testing and Sampling Results Q&amp;A<\/strong> <span style=\"color: #e81818\"><em>Updated 10\/6\/22<\/em><\/span><\/p>\n<p>Responses to questions from the August 30, 2022 Select Board meeting.&nbsp;<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/10\/Sudbury-GOL-Sampling-Rpt-9.29.22.Final_.pdf?version=6a902c7c61de6c4e130be789dadf8df0\">Sudbury GOL Sampling Report <em>September 29, 2022<\/em><\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/09\/SH_Sudbury-Select-Board-Info-Requests-Revised-09.15.22-2.pdf?version=dc8b0ea51f791dd6ab854a3be1232325\">Eversource Soil Testing Q&amp;A <em>September 21, 2022<\/em><\/a><\/p>\n<p>&nbsp;<\/p>\n<p><strong>Court Decisions<\/strong><\/p>\n<p><a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2022\/08\/SJC-12738_Opinion_Ruling-Affirming-Dismissal-of-case-against-MBTA.pdf?version=5700ccdf1ef1a8ad41203f5c2ba5d6c1\">SJC &#8211; MBTA Case Dismissal Affirmation. <em>September 22, 2020<\/em><\/a><\/p>\n<p><a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2022\/08\/Superior-Court-Decision-in-MEPA-Appeal_8.05.2021.pdf?version=6e0fe13ae8018581adc5d431f984d5db\">Superior Court &#8211; MEPA Appeal Decision. <em>August 5, 2021<\/em><\/a><\/p>\n<p><a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2022\/08\/SJC-12997_Opinion_Ruling-Dismissal-of-Siting-Board-Decision-Appeal.pdf?version=5700ccdf1ef1a8ad41203f5c2ba5d6c1\">SJC &#8211; Siting Board Appeal Dismissal. <em>June 25, 2021<\/em><\/a><\/p>\n<p><a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2022\/08\/Energy-Facilities-Siting-Board_Final-Decision_12.23.19.pdf?version=14fd254e463c1d78ba3d9184f437bc6d\">Energy Facilities Siting Board &#8211; Final Decision. <em>December 23, 2019<\/em><\/a><\/p>\n<p>&nbsp;<\/p>\n<p><strong>Town of Sudbury Decisions<\/strong><\/p>\n<p><a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/273\/2021\/02\/Eversource-Transmission-Line-DCR-Mass-Central-Rail-Trail-Final-Draft-Special-Conditions.pdf?version=a5fdfabc10673422c28faf877a5f2f70\">Conservation Commission &#8211; Order of Conditions<\/a><\/p>\n<p><a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2022\/08\/Eversource-ERP-Decision-21-1-183-Boston-Post-Road-Recorded.pdf?version=2a236eaa3ef6823bf6cc6cfd778dbaca\">Earth Removal Board &#8211; Earth Removal Permit<\/a><\/p>\n<p>&nbsp; &nbsp; <a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2023\/02\/ERB-21-1-Condition-15-Filing-20230201.pdf?version=da319a8b6c799c23172b90b0ec42f758\">Condition 15 Requirement Documentation <em>February 1, 2023<\/em><\/a><\/p>\n<p>&nbsp; &nbsp; <a href=\"https:\/\/sudbury.ma.us\/conservationcommission\/wp-content\/uploads\/sites\/273\/2022\/03\/Final-ERB-Sampling-Results.3.14.22.pdf?version=adabb9f7134f95eafbece191cff25365\">Supplemental Soil &amp; Groundwater Sampling Analysis &amp; Results <em>March 14, 2022<\/em><\/a><\/p>\n<p><a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2022\/08\/Cert-of-Appropriateness-HDC_22-15-Boston-Post-Road-near-Station-Road-Eversource.pdf?version=907252a4f353d79cbd57145559fbc172\">Historic Districts Commission &#8211; Certificate of Appropriateness<\/a><\/p>\n<p>&nbsp; &nbsp; &nbsp;<a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/09\/22-15-Boston-Post-Road-near-Station-Road-220919.pdf?version=57355fea9c037a5f8fc03e50ae87185f\">Updated Plans &#8211; Boston Post Rd Near Station Rd S<em>ubmitted September 19, 2022<\/em><\/a><\/p>\n<p><a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2022\/08\/Eversource-MCRT-SWMP-210127-Recorded.pdf?version=72068b523fdfbb6dde80f186693253ec\">Planning Board &#8211; Stormwater Management Permit<\/a><\/p>\n<p>&nbsp; &nbsp;&nbsp; <a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/10\/Eversource-Performance-Bond-220607.pdf?version=48f8a804c5401b0e0a82c3089b8c4248\">Permit Performance Bond&nbsp;<em>October 27, 2022<\/em><\/a><\/p>\n<p>&nbsp; &nbsp; &nbsp;<a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/09\/183-Boston-Post-Road-Eversource-SWMP-Modification.pdf?version=8eeb87551884d0fb51bc06073d44b9d7\">Stormwater Management Permit Modification <em>Approved September 14, 2022<\/em><\/a><\/p>\n<p>&nbsp; &nbsp; <a href=\"https:\/\/sudbury.ma.us\/pcd\/?p=3034\">Environmental Compliance Manual (Including Stormwater Pollution Prevention Plan [SWPPP]) <em>July 25, 2022<\/em><\/a><\/p>\n<p>&nbsp; &nbsp; <a href=\"https:\/\/sudbury.ma.us\/pcd\/?p=3035\">Environmental Compliance Manual &#8211; Associated Plans <em>July 25, 2022<\/em><\/a><\/p>\n<p>&nbsp; &nbsp; <a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/Lease-Agreement-between-Eversource-and-MBTA-220425.pdf?version=e59c8d6e351b8966f8ebf7d5bb153545\">&nbsp;Lease Agreement between Eversource and the MBTA <em>April 25, 2022<\/em><\/a><\/p>\n<p>&nbsp; &nbsp; &nbsp;<a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/MOU-between-Eversource-and-DCR-220329.pdf?version=2c9b77e8ace4fe851d07e6d2c0d654ac\">Memorandum of Understanding between Eversource and Department of Conservation and Recreation <em>March 29, 2022<\/em><\/a><\/p>\n<p>&nbsp; &nbsp; <a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/11\/Illicit-Discharge-Compliance-Statement-210930.pdf?version=af4e3bb9bb186f851de8d6d2c5abe2d0\">&nbsp;Illicit Discharge Compliance Statement <em>September 30, 2021<\/em><\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/05\/Grant-of-Location_Eversource_5.7.21.pdf?version=9e5e718afc8bdbf83fe7b0737241dec3\">Select Board &#8211; Grant of Location Permit. <em>May 5, 2021<\/em><\/a><\/p>\n<p>&nbsp; &nbsp; &nbsp;<a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/08\/GOL-responses-1-13-21.pdf?version=2bb590136d15da3fbb2776423265574a\">Q&amp;A &#8211; Grant of Location. <em>January 13, 2021<\/em><\/a><\/p>\n<p>&nbsp;<\/p>\n<p><strong>Other Decisions and Approvals<\/strong><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/pcd\/?p=3036\">404 General Permit from the US Army Corps of Engineers (USACE) <em>October 31, 2022<\/em><\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/pcd\/?p=3037\">USACE Work Start Notification Form <em>October 31, 2022<\/em><\/a><\/p>\n<p><a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/300\/2022\/03\/SHC-Edit-MOA-March-2022.pdf?version=5fb1a97d5fe564ff46dc3c935087e416\">Army Corps of Engineers Memorandum of Agreement<\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/historicalcommission\/wp-content\/uploads\/sites\/300\/2022\/11\/NAE-2017-01406-20221019_Executed_MOA.pdf?version=54ba26301c6d6120f3635f077efcd883\">Executed Memorandum of Agreement <em>October 19, 2022<\/em><\/a><\/p>\n<p><a href=\"https:\/\/eeaonline.eea.state.ma.us\/EEA\/emepa\/mepacerts\/2018\/sc\/eir\/15703%20FEIR%20Sudbury%20Hudson%20Transmission%20Reliability%20Project%20comments%20without%20large%20attachment.pdf\">Massachusetts Secretary of Energy and Environmental Affairs (EEA) on the final Environmental Impact Report (FEIR).<em> September 14, 2018<\/em><\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/08\/MCRT-Sudbury-to-Hudson-Eversource-DCR-MOA_CLEAN_220302_-executed-with-clean-exhibits.pdf?version=a72530dfa66d9ec184bba5e56117f896\">Eversource and Department of Conservation and Recreation (DCR) Memorandum of Understanding. <em>March 24, 2022<\/em><\/a><\/p>\n<p><a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/273\/2022\/08\/Environmental-Compliance-Manual.pdf?version=4cbd8b0e8f0fd714f1351431d89b5397\">Eversource Environmental Compliance Manual for Sudbury &#8211; Hudson Transmission Line Project. <em>May 25, 2022<\/em><\/a><\/p>\n<p>&nbsp;<\/p>\n<p><strong>Soil &amp; Groundwater Testing and Other Reports<\/strong><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/09\/Sudbury-GOL-Sampling-Rpt-8.30.22.Final_.pdf?version=affe8e6cae76b9c6521bc1a77f4de904\">Grant of Location Soil &amp; Groundwater Assessment Results <em>September 8, 2022<\/em><\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/conservationcommission\/wp-content\/uploads\/sites\/273\/2022\/02\/S-H-SGMP-Update_FINAL-1.31.22.pdf?version=181090dcf006e6823e4175dee15cc0a1\">Soil &amp; Groundwater Management Plan (SGM). <em>January 2022<\/em><\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/08\/SGMP-ERB-Memo.5.4.22.pdf?version=29739ec062cab2fc22e2c825f4d8cc4f\">SGM Memo <em>May 4, 2022<\/em><\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/conservationcommission\/wp-content\/uploads\/sites\/273\/2022\/03\/Final-ERB-Sampling-Results.3.14.22.pdf?version=adabb9f7134f95eafbece191cff25365\">Earth Removal Board Supplemental Soil &amp; Groundwater Sampling Results. <em>March 14, 2022<\/em><\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/08\/Eversource-Soil-Sampling-Plan-10-15-21-Final.pdf?version=811814577ab42e4e68712cf4ecbf091e\">Earth Removal Board Supplemental Soil &amp; Groundwater Sampling Plan. <em>Oct. 15, 2021<\/em><\/a><\/p>\n<p><a href=\"https:\/\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/273\/2022\/07\/67849_CWF_Monitoring_SudburyMA_Results-Jun16-2022.pdf?version=27faebf5d5196d828bd1db020beee15a\">Conservation Commission &#8211; Coldwater Fishery Report Results. <em>June 2022<\/em><\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/07\/EversourceBoringAndSamplingPlan.06.13.22.pdf?version=644249ce1311c23475e1344511e832e7\">Grant of Location (GOL) Sampling Plan. <em>June 13, 2022 <\/em><\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/conservationcommission\/wp-content\/uploads\/sites\/273\/2021\/11\/SudConComSubmission_ERBSamplingActivities_Oct20_2021-Revised.pdf?version=9eeec74df7d5b117196ea0110d52a6d5\">Conservation Commission \u2013 Additional Sampling Activities. <em>October 20, 2021 <\/em><\/a><\/p>\n<p><a href=\"https:\/\/s3-us-west-2.amazonaws.com\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/273\/2020\/06\/ConservationCommission_2020_Jul_08_supporting_materials_5.pdf?version=c744e583a275622e0f977fe480843daf\">Conservation Commission Summary of Soil and Groundwater Analytical Results and Subsurface Media Management. <em>June 12, 2020<\/em><\/a><\/p>\n<p>&nbsp;<\/p>\n<p><strong>8\/11\/2022: Pre-Construction Work<\/strong><br \/>\nAs a part of necessary pre-construction efforts for the Sudbury to Hudson (115 kV) Underground Transmission Project, Eversource, through contractors (BOND Civil &amp; Utility Construction and E.T. &amp; L. Corp.), will be performing environmental surveys along the inactive Massachusetts Bay Transportation (\u201cMBTA\u201d) rail corridor.<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/08\/SH_MBTA-Corridor-Survey-DH-Aug.22.pdf?version=06e867a305c23e99ad2015d7f0d33b31\">Official Notification from Eversource<\/a><\/p>\n<p>&nbsp;<\/p>\n<p><strong>6\/14\/22: Survey Work and Soil Sampling<\/strong><\/p>\n<p>Over the next several weeks, Eversource contractors (Weston &amp; Sampson) will be conducting sampling, through soil borings, at four road crossings (Dutton Road, Peakham Road, Horse Pond Road and Union Avenue) in Sudbury.<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2022\/07\/EversourceBoringAndSamplingPlan.06.13.22.pdf?version=644249ce1311c23475e1344511e832e7\">Official Notification and GOL Sampling Plan<\/a><\/p>\n<p>&nbsp;<\/p>\n<p><strong>11\/29\/21: Survey Work and Soil Sampling<\/strong><\/p>\n<p>Eversource contractors will be conducting soil sampling in the MBTA corridor. In Sudbury, soil sampling will be completed within the inactive MBTA corridor. Access to the right-of-way will take place of off Dutton Road, Peakham Road, Horse Pond Road, Union Avenue and Boston Post Road.<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/11\/SH-Sudbury-Nov-2021-door-hanger.pdf?version=1c13069e0dece40f2f69640694947fb8\">Official Notification from Eversource<\/a><\/p>\n<p>&nbsp;<\/p>\n<p><strong>11\/12\/21: Grant of Location (GOL) Sampling Plan<\/strong><\/p>\n<p><span style=\"text-decoration: underline\"><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/11\/S-H-GOL-Sampling-Plan.10.26.21.Final_.pdf?version=5a190808223b0bc106d1bbbd501a58e1\">PFAS Sampling Plan<\/a><\/span> to meet Conditions 43 and 44 in the GOL permit prepared by Weston &amp; Sampson Engineers on behalf of Eversource.<\/p>\n<p>&nbsp;<\/p>\n<p><strong>10\/26\/21: Eversource General Survey Work in MBTA Corridor<\/strong><\/p>\n<p>Eversource contractors will be performing assessments of the Sudbury to Hudson Reliability Project route this week. Residents, visitors, and Town officials in the community may see company representatives in the MBTA corridor and streets starting soon.&nbsp;<\/p>\n<p>These contractors will have proper identification however, if there are any concerns or questions, please call 1-800-793-2202 or send a message to <a href=\"mailto:projectinfo@eversource.com\">ProjectInfo@eversource.com<\/a>.<\/p>\n<p>&nbsp;<\/p>\n<p><strong>5\/10\/21: Grant of Location &#8211; Voted by Select Board 5\/5\/21<\/strong><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/05\/Grant-of-Location_Eversource_5.7.21.pdf?version=9e5e718afc8bdbf83fe7b0737241dec3\">Order for Location for Lines, Wires and Cables<\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/05\/B-Klein_-Obtain-Grant-of-Location-for-Eversource.pdf?version=dac5b820916050ebab6fc7e1e6b49238\">In Board of 5\/5\/21 Vote<\/a><\/p>\n<p>&nbsp;<\/p>\n<p><strong>3\/16\/21: SJC Clarification Letters &#8211; Energy Facilities Siting Board<\/strong><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/03\/SUDBURY-CLERKS-LETTER-SJC-2-25-21-E-FILE.pdf?version=b318151339a1cfa7fbb216df2c05d865\">Letter Dated 2\/25\/21<\/a> on behalf of EFSB<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/03\/SUDBURY-CLERKS-LETTER-SJC-3-12-21-E-FILE-FINAL.pdf?version=be2acf8fe040db1c91a66772bba5d5a0\">Letter Dated 3\/12\/21<\/a> on behalf of EFSB<\/p>\n<p>&nbsp;<\/p>\n<p><strong>3\/9\/21: Post-Argument Filing Letter &#8211; Town of Sudbury<\/strong><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/03\/Let-Clerk-3-4-21-Rule-22-Post-Argument-Letter-FINAL.pdf?version=0883f8e87a81cbc94c869b311adfcd4e\">Letter Dated 3\/4\/21<\/a> from BCK Law on behalf of the Town.<\/p>\n<p>&nbsp;<\/p>\n<p><strong>2\/5\/21: SJC Appeal Amicus Brief &#8211; National Grid<\/strong><\/p>\n<p><a href=\"https:\/\/s3-us-west-2.amazonaws.com\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2021\/02\/Amicus-Brief-New-England-Power-final-2.5.21.pdf?version=108a861330920cdbf57ed21e1d3e2fde\"><span style=\"text-decoration: underline\">Amicus Brief Dated 2\/5\/21<\/span><\/a> in the pending SJC appeal filed on behalf of the following Amicus Curiae New England Power Company DBA National Grid.<\/p>\n<p>&nbsp;<\/p>\n<p><strong>2\/3\/21: SJC Appeal Amicus Brief<\/strong><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/02\/Amicus-Brief.2.pdf?version=e9a89f21494363020c8b563cf8f3449d\"><span style=\"text-decoration: underline\">Amicus Brief Dated 2\/3\/21<\/span><\/a> in the pending SJC appeal filed on behalf of the following Amici:&nbsp;<\/p>\n<ul>\n<li style=\"list-style-type: none\">\n<ul>\n<li>The Massachusetts Bicycle Coalition [Massbike]<\/li>\n<li>The Mass. Central Rail Trail Coalition<\/li>\n<li>The East Quabbin Land Trust<\/li>\n<li>The East Coast Greenway Alliance<\/li>\n<li>The Rails to Trails Conservancy<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n<p>&nbsp;<\/p>\n<p><strong>1\/28\/21: SJC Appeal Amicus Brief<\/strong><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/03\/SJC-12997_07_Amicus_Gee_Brief.pdf?version=c159480ff3df0734466a86be82c30ed1\"><span style=\"text-decoration: underline\">Amicus Brief Dated 1\/28\/21<\/span><\/a> in the pending SJC appeal filed by Kin K. Gee.<\/p>\n<p>&nbsp;<\/p>\n<p><strong>11\/30\/20: Chapter 91 Public Hearing Presentations &#8211; Bridge 127 &amp; Bridge 128<\/strong><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/02\/S-H-MCRT-Ch.-91-Public-Hearing-Presentation-Bridge-127-20201130.pdf?version=5d17aa4982c09c518cc68e34c6416f39\"><span style=\"text-decoration: underline\">Bridge 127 &#8211; Chapter 91 Hearing Presentation<\/span><\/a><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/02\/S-H-MCRT-Ch.-91-Public-Hearing-Presentation-Bridge-128-20201130.pdf?version=cd5647cc0320b472bf5c416f4ed98e6d\"><span style=\"text-decoration: underline\">Bridge 128 &#8211; Chapter 91 Hearing Presentation<\/span><\/a><\/p>\n<p>&nbsp;<\/p>\n<p><strong>Update 10\/5\/20: Town of Sudbury Appeals Status<\/strong><\/p>\n<p>Whether the final decision of the Energy Facilities Siting Board (board) approving, with conditions, (a) a new underground transmission line located primarily in Sudbury and Hanson, within an inactive Massachusetts Bay Transportation Authority right of way and an in-street segment; and (b) individual and comprehensive zoning exemptions from the zoning bylaws of the towns of Sudbury, Hudson, and Stow, should be set aside.<\/p>\n<ol>\n<li>Supreme Judicial Court (SJC) Land Court Appeal\n<ul>\n<li>TOWN OF SUDBURY &amp; another vs. ENERGY FACILITIES SITING BOARD. NO. SJC-12997<\/li>\n<li><a href=\"https:\/\/www.ma-appellatecourts.org\/docket\/SJC-12997\">SJC Docket Information<\/a><\/li>\n<\/ul>\n<\/li>\n<\/ol>\n<p>&nbsp;<\/p>\n<p><strong>Update 8\/24\/20: Town of Sudbury Appeals Status<\/strong><\/p>\n<p>The Town of Sudbury is currently appealing three issues pertaining to the Eversource Transmission Line project: SJC Land Court Case, EFSB Decision and MEPA Certificate. Please see below for details.<\/p>\n<ol>\n<li>Supreme Judicial Court (SJC) Land Court Appeal\n<ul>\n<li>TOWN OF SUDBURY V. MASSACHUSETTS BAY TRANSPORTATION AUTHORITY (MBTA) AND NSTAR ELECTRIC COMPANY DBA EVERSOURCE ENERGY. No. SJC-12738<\/li>\n<li>Appeal of the Land Court judgment alleging that the MBTA violated Massachusetts prior public use doctrine, which precludes land taken for a particular public use to be diverted to an inconsistent public use without plain and explicit authorizing legislation. Oral arguments before the SJC were held on October 1, 2019. On April 29, 2020 the SJC waived its 130 day rule, giving itself more time to issue a decision.<\/li>\n<li><a href=\"https:\/\/boston.suffolk.edu\/sjc\/pop.php?csnum=SJC_12738\">Oral Argument Video<\/a><\/li>\n<li><a href=\"https:\/\/www.ma-appellatecourts.org\/docket\/SJC-12738\">SJC Docket Information<\/a><\/li>\n<li><a href=\"https:\/\/s3-us-west-2.amazonaws.com\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2020\/08\/SUDB-MBTA-SJC-REPLY-BRIEF.pdf?version=b1e4a0774e02e51dc99a7bab7bc6e65d\">Town of Sudbury Reply Brief<\/a> 5\/21\/2019<\/li>\n<\/ul>\n<\/li>\n<li>Energy Facilities Siting Board (EFSB) Appeal\n<ul>\n<li>TOWN OF SUDBURY v. ENERGY FACILITIES SITING BOARD<\/li>\n<li>Appeal of the December 18, 2019 EFSB decision to approve the Eversource Transmission Line project. In July 2020, a joint motion was entered to consolidate the Town of Sudbury\u2019s appeal (SJ-2020-0026) with Protect Sudbury\u2019s appeal (SJ-2020-0029). The Town\u2019s appeal alleges the EFSB committed errors of law, that the EFSB\u2019s decision to approve the project is unwarranted by facts on the record, and that the Siting Board \u201cerroneously determined that subject to its required conditions, the Project is necessary for the purpose alleged, and will serve the public convenience, and is consistent with the public interest.\u201d Oral arguments have not yet been scheduled.<\/li>\n<li><a href=\"https:\/\/www.ma-appellatecourts.org\/docket\/SJ-2020-0026\">SJC Docket Information<\/a><\/li>\n<li><a href=\"https:\/\/s3-us-west-2.amazonaws.com\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2020\/08\/Town-of-Sudbury-v-Energy-Facilities-Siting-Board-BCK-Law-letter-to-Clerk-Maura-Doyle_County-of-Suffolk.pdf?version=5a269e1e71a90c7bad734eef6c680010\">Town of Sudbury Petition for Appeal<\/a> 1\/27\/20<\/li>\n<\/ul>\n<\/li>\n<li>Massachusetts Environmental Policy Act Office (MEPA) Certificate Appeal\n<ul>\n<li>TOWN OF SUDBURY V. KATHLEEN THEOHARDIES, IN HER CAPACITY AS SECRETARY OF THE EXECUTIVE OFFICE OF ENERGY &amp; ENVIRONMENTAL AFFAIRS, AND NSTAR ELECTRIC COMPANY DBA EVERSOURCE ENERGY SUFFOLK SUPERIOR COURT<\/li>\n<li>Appeal of the MEPA Certificate granted for the Final Environmental Impact Report (FEIR) filed for the Eversource Transmission Line project.<\/li>\n<li><a href=\"https:\/\/www.masscourts.org\/eservices\/home.page.8\">Superior Court Docket Information<\/a>\n<ol style=\"list-style-type: lower-alpha\">\n<li style=\"text-align: justify\">Court Department = The Superior Court<\/li>\n<li style=\"text-align: justify\">Court Division = Suffolk County Civil<\/li>\n<li>\n<p style=\"text-align: justify\">Case Number =&nbsp;2084CV00151<\/p>\n<\/li>\n<\/ol>\n<\/li>\n<li><a href=\"https:\/\/s3-us-west-2.amazonaws.com\/cdn.sudbury.ma.us\/wp-content\/uploads\/sites\/342\/2020\/08\/Town-of-Sudbury-v-Kathleen-Theoharides-NSTAR-Electric-Company-dba-Eversource-Energy-KP-Law-letter-to-Maura-Healey-Kathleen-Theohardies-1.pdf?version=0ef7ea52053f3dd51af0a91a3002b614\">Town of Sudbury Judicial Review Request<\/a> 1\/17\/20<\/li>\n<\/ul>\n<\/li>\n<\/ol>\n<p>&nbsp;<\/p>\n<p><b><span style=\"color: black\">Update 8\/2\/20: Eversource &amp; Mass Central Rail Trail Stormwater Management Application<\/span><\/b><\/p>\n<p><span style=\"color: black\">NSTAR Electric Company d\/b\/a Eversource Energy (\u201cEversource\u201d) and the Massachusetts Department of Conservation (\u201cDCR\u201d), have filed an application with the Planning Board for a Major Stormwater Management Permit for construction of the Sudbury-Hudson Transmission Reliability and Mass Central Rail Trail Project. The Project includes construction of a new 115-kV underground transmission line and a multi-use path within an existing inactive railroad right-of-way, which will require removal of the existing rails and ties; vegetation clearing; grading; installation of the underground transmission line, duct bank, and manholes; installing a 14-foot-wide gravel base; paving of the 10-foot-wide rail trail; installation of stormwater management features; and site restoration. <\/span><span style=\"color: #212529;background: white\">The Sudbury Planning Board held a public hearing on August 12, 2020 at 7:00 PM as a virtual meeting.<\/span><\/p>\n<p><span style=\"color: black\">For more details and application materials, please visit <a href=\"https:\/\/sudbury.ma.us\/planning\/?p=2442\"><span style=\"color: #0563c1\">https:\/\/sudbury.ma.us\/planning\/?p=2442<\/span><\/a> <\/span><\/p>\n<p>&nbsp;<\/p>\n<h4>Applications<\/h4>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2020\/10\/MassDEP-Notice-of-License-Public-Comment-Notice-for-Bridge-127-200827.pdf?version=64e6507172ea9405616a69ceb765b629\">MassDEP Notice of License Public Comment Notice for Bridge 127 200827<\/a> (August 27, 2020)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2020\/10\/MassDEP-Notice-of-License-Public-Comment-Notice-for-Bridge-128-200827.pdf?version=ded891d3f1808cf99fb03c1b013b2c87\">MassDEP Notice of License Public Comment Notice for Bridge 128 200827<\/a> (August 27, 2020)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2020\/10\/Chapter-91-Request-for-Extended-Term-200702.pdf?version=cb121ff74d0dda6c366c6b1bb0efc896\">Chapter 91 Request for Extended Term 200702<\/a> (July 2, 2020)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2020\/09\/SudtoHud-CH91-Compiled_20200527.pdf?version=6f6d604c26c5f623deeae7cb22b682d8\">Sudbury-Hudson Transmission Reliability and Mass Central Rail Trail Project: Bridge Replacements by VHB<\/a> (May 27, 2020)<\/p>\n<p>&nbsp;<\/p>\n<h4>Correspondence<\/h4>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/10\/Letter-from-Concerned-CItizens-to-USACE-with-Questions-re-Sudbury-Hudson-Rel.-Project-Sec-106.pdf?version=8e09e428cc45af452f0bb68a0b266b7d\">Letter to USACE from Concerned Citizens<\/a> (October 13, 2021)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/10\/NITU-Request-to-STB-for-MCRT-09.28.21_ltr.pdf?version=3be0ad4ef0d69806a9bb024376efe13e\">Letter to Surface Transportation Board Chair Oberman from Select Board<\/a> (October 6, 2021)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-content\/uploads\/sites\/342\/2021\/10\/Select-Board-letter_Gov-Baker-Eversource-CEO-Nolan.pdf?version=131f48180ba3a0e95004673b3470cbac\">Letter to Governor Baker and Eversource CEO Nolan from Select Board<\/a> (October 5, 2021)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1953\">Bolton Conservation Commission Letter of Support<\/a> (June 10, 2019)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1712\">Town Response to Final Impact Environmental Report<\/a> (September 7, 2018)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1700\">Notification of Soil Borings &amp; Test Pitting on MBTA ROW<\/a> (August 27, 2018)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1654\">Email Regarding Final Environmental Impact Report<\/a> (July 30, 2018)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1346\">Letter Regarding MAPC Meeting on Mass Central Rail Trail<\/a> (July 31, 2017)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1313\">Notification&nbsp;Regarding Field Activities<\/a> (June 20, 2017)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1302\">U.S. Fish and Wildlife Service&nbsp;Letter<\/a>&nbsp;(June 14, 2017)&nbsp;<\/p>\n<p><span style=\"color: #0066cc\"><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1284\"><span style=\"color: #0066cc\">Right of Way Spring Aerial Helicopter Patrols from Eversource <\/span><\/a>&nbsp; <span style=\"color: #000000\">(May 17, 2017)<\/span><\/span><\/p>\n<p><span style=\"color: #0066cc\"><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=3217\">Protect Sudbury Response From MassDOT<\/a>&nbsp; <span style=\"color: #000000\">(April 4, 2017)<\/span><\/span><\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=2912\">Senator Elizabeth Warren, Congresswoman Katherine Clark and Congresswoman Niki Tsongas Eversource Concerns Letter<\/a> (October 18, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1106\">Organization for the Assabet River (OARS) Letter<\/a> (September 6, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1077\">Friends of the Assabet River National Wildlife Refuge Letter<\/a> (August 14, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1062\">Survey Work Continuation Notification<\/a> (July 11, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1042\">Town Manager&nbsp;Letter to Joint Committee&nbsp;on Telecommunications, Utilities and Energy Chairmen<\/a> (June 20, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1023\">Survey Work Continuation Notification <\/a>(June 14, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1012\">Board of Selectmen Letter to Energy &amp; Environmental Affairs Sec.<\/a> (May 24, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=994\">Eversource FAQ<\/a> (May 11, 2016- UPDATED June 2, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=958\">Eversource Notification of Survey Work<\/a>&nbsp; (May 2, 2016- UPDATED May 3, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=898\">Senator Eldridge, Representative Hogan and Rep Gentile Letter<\/a> (March 25, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=895\">Governor Baker Office Letter<\/a> (March 18, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=891\">Board of Selectmen&nbsp;Letter<\/a> (March 25, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=2657\">Board of Selectmen Letter<\/a> (March 17, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/townmanager\/2016\/03\/16\/letter-sent-to-governor-baker-regarding-eversource-project\/\">Town Manager Letter<\/a>&nbsp;(March 14, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/conservationcommission\/?p=1152\">Conservation Commission Letter<\/a>&nbsp;(March 15, 2015)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/historicdistricts\/?p=612\">Historic Districts Commission Letter<\/a> (March 14, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=888\">Historical Society Letter<\/a> (March 18, 2016)<\/p>\n<p>&nbsp;<\/p>\n<h4>Litigation<\/h4>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1361\">Complaint for Declaratory Judgment and Injunctive Relief_MBTA<\/a> (September 27, 2017)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1304\">Sudbury Petition to Intervene<\/a> (June 15, 2017)<\/p>\n<p><a href=\"http:\/\/170.63.40.34\/DPU\/FileRoomAPI\/api\/Attachments\/Get\/?path=efsb17-02%2fNoticeofHearing5417.pdf\">Eversource Petition to Construct Transmission Line &#8211; EFSB Hearing Notice<\/a> (May 25, 2017)<\/p>\n<p>&nbsp;<\/p>\n<h4>Meetings<strong><br \/>\n<\/strong><\/h4>\n<p><a href=\"https:\/\/sudbury.ma.us\/conservationcommission\/eversource-mass-central-rail-trail-notice-of-intent\/\">Notice of Intent Hearing information and documentation filed with the Conservation Commission<\/a> (March 2020 &#8211; Present)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=3295\">MEPA&nbsp;Scoping Session<\/a> (June&nbsp;12, 2017)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1270\">Commonwealth of Massachusetts Energy Facilities Siting Board &#8211; Public Hearing <\/a>(May 25, 2017)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=2906\">Board of Selectmen Meeting with Presentation from Eversource <\/a>(October 26, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=985\">Eversource Meeting<\/a> with Town staff (April 5, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=2660\">Eversource Discussion<\/a> Excerpt from&nbsp;Feb 2, 2016 Board of Selectmen Meeting<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=855\">Open House Postcard<\/a>&nbsp;(March 16, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=2661\">Memo From Selectman Simon<\/a> (Re: 3\/7\/16 Town of Hudson Board Meeting)<\/p>\n<p>&nbsp;<\/p>\n<h4>Presentations<\/h4>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1116\">Presentation by Eversource <\/a>to Board of Selectmen on 10\/26\/16<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1094\">Routing and Design Re-Evaluation Results<\/a> to Board of Selectmen at 09\/06\/16 Meeting.<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=2603\">Presentation by Eversource<\/a> to Board of Selectmen at 02\/02\/16 Meeting. (<span style=\"text-decoration: underline\">Revised 3\/24\/16<\/span>)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=2662\">Presentation by Protect Sudbury<\/a> to Board of Selectmen on 03\/08\/16<\/p>\n<p>&nbsp;<\/p>\n<h4>Press Releases<\/h4>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=3409\">Sudbury Files Suit Against MBTA<\/a> (September 28, 2017)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=3225\">Developments Continue in Sudbury\u2019s Fight against Eversource<\/a> (April 13, 2017)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1105\"><span style=\"color: #0066cc\">OARS Raises News Concerns about \u2018Ecologically Damaging\u2019 Eversource Project Press Release<\/span><\/a> (October 17, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1069\"><span style=\"color: #0066cc\">Eversource Project an \u201cExorbitant\u201d Financial Burden Press Release<\/span><\/a> (August 2, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/?p=1039\"><span style=\"color: #0066cc\">Selectmen &#8220;Deeply Concerned&#8221; About Eversource Herbicide Use Press Release <\/span><\/a>(June 16, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=2703\"><span style=\"color: #0066cc\">Board of Selectmen Press Release<\/span><\/a> (April 7, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=2692\"><span style=\"color: #0066cc\">Board of Selectmen Press Release<\/span><\/a> (April 1, 2016)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/2016\/03\/18\/sudbury-stands-together-to-oppose-overhead-power-lines\/\"><span style=\"color: #0066cc\">Sudbury Stands Together Press Release<\/span><\/a> (March 18, 2016)<\/p>\n<p>&nbsp;<\/p>\n<h4>Reports<\/h4>\n<p><a href=\"http:\/\/projects.vhb.com\/sudbury-hudson\/feir\/\">MEPA Final Environmental Impact Report filed by&nbsp;VHB on behalf of Eversource<\/a>&nbsp;(July 2, 2018)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/selectboard\/?p=2663\">1966 Underground Power Lines Study<\/a> (introduction from League of Women Voters)<\/p>\n<p>&nbsp;<\/p>\n<h4>Web Resources<\/h4>\n<p><a href=\"http:\/\/www.iso-ne.com\/\">ISO-New England website<\/a> (non-profit organization that issued report citing deficiencies in electric system)<\/p>\n<p><a href=\"https:\/\/sudbury.ma.us\/?p=5204\" target=\"_blank\" rel=\"noopener noreferrer\">Email Signup<\/a> (please click to sign up to receive updates regarding the Eversource project from the Town Manager)<\/p>\n<p>&nbsp;<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Work on the project is in progress. See full article for project schedule, updates and general information. <a href=\"https:\/\/sudbury.ma.us\/selectboardsoffice\/2022\/12\/12\/eversource-transmission-line-project-information\/\" aria-label=\"Read full article about EVERSOURCE Sudbury to Hudson Transmission Line Project\">Read full article<span class=\"meta-nav\">&rarr;<\/span><\/a><\/p>\n","protected":false},"author":81,"featured_media":1701,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"inline_featured_image":false},"categories":[1,6],"tags":[],"_links":{"self":[{"href":"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-json\/wp\/v2\/posts\/869"}],"collection":[{"href":"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-json\/wp\/v2\/users\/81"}],"replies":[{"embeddable":true,"href":"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-json\/wp\/v2\/comments?post=869"}],"version-history":[{"count":265,"href":"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-json\/wp\/v2\/posts\/869\/revisions"}],"predecessor-version":[{"id":4238,"href":"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-json\/wp\/v2\/posts\/869\/revisions\/4238"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-json\/wp\/v2\/media\/1701"}],"wp:attachment":[{"href":"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-json\/wp\/v2\/media?parent=869"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-json\/wp\/v2\/categories?post=869"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/sudbury.ma.us\/selectboardsoffice\/wp-json\/wp\/v2\/tags?post=869"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}