Town-wide Roadway Resurfacing Schedule

Paving schedule:

1) July 9th, 10th and 11th milling of Fairbank Rd., Maynard Rd. (Maynard Rd. is for the Water district), then moving to Nobscot. 

2) Work on handicap ramps and structures is scheduled the week of the 16th (approx. 2 weeks of work).                                           

3) Final paving upon completion of ramps (tentatively the week of July 30).

Work will start at 7 AM and may continue into the evening hours. 

All dates are dependent on weather, sub-contractors’ schedules and any other unforeseen issues. 