Please be advised that the Sudbury Water District will be performing construction at the intersection of Marlboro Road and Willis Road to replace water main gate valves and pipe. The work is being performed to replace old inoperative gate valves.

PROJECT TIMELINE (weather permitting):
Tuesday, June 20th -23nd

CONSTRUCTION HOURS:
Monday-Friday, 7:30 AM – 3:00 PM

INTERRUPTION OF SERVICE:
Water will be turned off on Marlboro Road from house # 126 to house # 280, Willis Road from house # 82 to house # 228, all of Craig Lane, all of Hamblin Lane, and Meachen Road, house #’s 2 & 3, for approximately 7 hours during the hours of 8:00 AM – 3:00 PM